Garden Valley Technologies is excited to extend its fiber optic networks and offer products and services to residential and business customers located in the city of Thief River Falls. Construction on this large project began in the spring of 2020 and is estimated to wrap-up in the summer of 2021. GVT has divided the project up into nine zones with an estimated 3,500 fiber drops for service. The company anticipates having 2,500 of the 3,500 drops complete by the end of 2020. The remaining 1,000 drops will primarily be in zones 3, 4, 7 and 8 and will be completed in the summer of 2021.
If you signed up for service prior to September 21, 2020, GVT will make every effort to provide service to your home as inducted below.
Here is a breakdown of information by zone (please refer to the TRF Zone Map below to see what Zone you are in):
CO Zone: Currently under construction and services will start to be activated at the end of October 2020
Zone 1: Currently under construction and services will start to be activated December 2020
Zone 2: Currently under construction and services will start to be activated December 2020
Zone 3: Currently under construction and services will start to be activated February 2021
(only for those who signed up prior to September 21, 2020).
All new sign-ups will be installed summer of 2021.
Zone 4: Currently under construction and services will start to be activated January 2021
(only for those who signed up prior to September 21, 2020).
All new sign-ups will be installed summer of 2021.
Zone 5: Currently under construction and services will start to be activated at the end of December 2020
Zone 6: Currently under construction and services will start to be activated January 2021
Zone 7: Currently under construction and services will start to be activated end of January 2021
(only for those who signed up prior to September 21, 2020).
All new sign-ups will be installed summer of 2021.
Zone 8: Currently under construction and services will start to be activated February 2021
(only for those who signed up prior to September 21, 2020).
All new sign-ups will be installed summer of 2021.